§ 110.8. Notice of completion of construction--Certification
Oklahoma Statutes AnnotatedTitle 82. Waters and Water Rights
82 Okl.St.Ann. § 110.8
§ 110.8. Notice of completion of construction--Certification
A. Certificates of completion of works from the Oklahoma Water Resources Board shall be required before any water may be impounded by a new dam or before water may be impounded at an elevation higher than that previously authorized by the Board at an existing dam which has been modified. Said certificate shall contain the date of approval of plans and specifications for the dam, date construction was completed on said dam, and any other conditions as may be required by the Board.
Credits
Laws 1992, c. 185, § 8, eff. July 1, 1992.
82 Okl. St. Ann. § 110.8, OK ST T. 82 § 110.8