§ 105.15. Time for commencement of works
Oklahoma Statutes AnnotatedTitle 82. Waters and Water Rights
82 Okl.St.Ann. § 105.15
§ 105.15. Time for commencement of works
A. Any permit shall expire unless the applicant begins construction of the works within two (2) years of the issuance of the permit by the Board. The Board may, as necessary and deemed appropriate under the circumstances, extend the time for the beginning of construction beyond the time allowed in the permit for good cause shown, such as engineering difficulty or other valid reason over which the applicant has no control.
Credits
Laws 1972, c. 256, § 15. Laws 1981, c. 35, § 3, eff. April 8, 1981; Laws 1993, c. 164, § 4, emerg. eff. May 10, 1993.
82 Okl. St. Ann. § 105.15, OK ST T. 82 § 105.15
Current with emergency effective legislation through Chapter 257 of the Second Regular Session of the 59th Legislature (2024). Some sections may be more current, see credits for details.