61 Okl.St.Ann. § 113.1
§ 113.1. Partial payment--Retainage
<Text as amended by Laws 2022, c. 238, § 24. See also, text as amended by Laws 2022, c. 315, § 1.>
A. A public construction contract shall provide for partial payment based upon work completed. The contract shall provide that up to five percent (5%) of all partial payments made shall be withheld as retainage until the project is fifty percent (50%) complete as determined by the awarding agency. When the awarding public agency determines that the project is at least fifty percent (50%) complete, the retainage amount shall be two and one-half percent (2.5%) with respect to the balance of the work.
B. The Department of Transportation or the Oklahoma Turnpike Authority shall not withhold retainage on public construction contracts awarded by the Department or the Authority.
C. The Department of Transportation shall not withhold retainage or require any bond on projects awarded to railroads on the railroad's privately owned or operated rail property.

Credits

Laws 1977, c. 74, § 2, eff. Oct. 1, 1977; Laws 1983, c. 67, § 1, emerg. eff. April 29, 1983; Laws 1995, c. 200, § 2, emerg. eff. May 19, 1995; Laws 1997, c. 278, § 4, emerg. eff. May 27, 1997; Laws 2006, c. 271, § 19, eff. July 1, 2006; Laws 2011, c. 99, § 1, eff. Nov. 1, 2011; Laws 2022, c. 238, § 24, eff. Nov. 1, 2022.
61 Okl. St. Ann. § 113.1, OK ST T. 61 § 113.1
Current with emergency effective legislation through Chapter 257 of the Second Regular Session of the 59th Legislature (2024). Some sections may be more current, see credits for details.
End of Document