Gas Demand Response Pilot Program

NY-ADR

3/10/21 N.Y. St. Reg. PSC-10-21-00009-P
NEW YORK STATE REGISTER
VOLUME XLIII, ISSUE 10
March 10, 2021
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
PROPOSED RULE MAKING
NO HEARING(S) SCHEDULED
 
I.D No. PSC-10-21-00009-P
Gas Demand Response Pilot Program
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following proposed rule:
Proposed Action:
The Commission is considering a petition filed by Consolidated Edison Company of New York, Inc. on February 10, 2021, requesting to extend the term of its three-year Gas Demand Response Pilot Program by one year.
Statutory authority:
Public Service Law, sections 5, 5(2), 65 and 66
Subject:
Gas Demand Response Pilot Program.
Purpose:
To provide promote natural gas system reliability by encouraging reductions of natural gas demand during peak gas demand days.
Substance of proposed rule:
The Public Service Commission (Commission) is considering a petition (Petition) filed by Consolidated Edison Company of New York, Inc. (Con Edison or Company) on February 10, 2021, requesting to extend the term of its Smart Solutions for Natural Gas Customers Demand Response Pilot Program (Pilot Program) by one year. The Company is not seeking any additional funding for the one-year extension of the Pilot Program.
In the petition, Con Edison notes that, since the initial 2018/2019 Winter Season, the Company has gained valuable insight into customer engagement and third-party participation, program incentive levels and measures to streamline event dispatch. The Company notes, however, that it has encountered some challenges in gathering sufficient data due to mild winters that have limited the number of events and the usefulness of the data. Therefore, Con Edison is requesting that the Commission approve a one-year extension of the Pilot Program to allow the Company to continue testing to gather data needed to achieve the Pilot Program’s overall goals, including, among other things, collecting information on successful customer gas use reduction strategies, informing the process of setting program incentive levels and testing customer engagement. The Company also requests that the Commission authorize the Secretary to grant any future requests to extend the term of the Pilot Program.
The full text of the petition and the full record of the proceeding may be reviewed online at the Department of Public Service web page: www.dps.ny.gov. The Commission may adopt, reject, or modify, in whole or in part, the action proposed, and may resolve other related matters.
Text of proposed rule and any required statements and analyses may be obtained by filing a Document Request Form (F-96) located on our website http://www.dps.ny.gov/f96dir.htm. For questions, contact:
John Pitucci, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: [email protected]
Data, views or arguments may be submitted to:
Michelle Phillips, Secretary, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 474-6530, email: [email protected]
Public comment will be received until:
60 days after publication of this notice.
Regulatory Impact Statement, Regulatory Flexibility Analysis, Rural Area Flexibility Analysis and Job Impact Statement
Statements and analyses are not submitted with this notice because the proposed rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(17-G-0606SP8)