Whether to Grant, Deny or Modify, in Whole or in Part the Petition of Con Edison to Grant Easem...

NY-ADR

11/7/12 N.Y. St. Reg. PSC-45-12-00010-P
NEW YORK STATE REGISTER
VOLUME XXXIV, ISSUE 45
November 07, 2012
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
PROPOSED RULE MAKING
NO HEARING(S) SCHEDULED
 
I.D No. PSC-45-12-00010-P
Whether to Grant, Deny or Modify, in Whole or in Part the Petition of Con Edison to Grant Easements to Millwood Fire District
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following proposed rule:
Proposed Action:
The Commission is considering the petition of Consolidated Edison of New York, Inc. to grant certain easements to Millwood Fire District over a portion of District Tax Map ID No. 81.09-3-1, Town of New Castle, New York.
Statutory authority:
Public Service Law, sections 2(12), (13), 66(1) and 70(1)
Subject:
Whether to grant, deny or modify, in whole or in part the petition of Con Edison to grant easements to Millwood Fire District.
Purpose:
Whether to grant, deny or modify, in whole or in part the petition of Con Edison to grant easements to Millwood Fire District.
Substance of proposed rule:
The Public Service Commission is considering whether to grant, deny or modify, in whole or part, the petition of Consolidated Edison Company of New York, Inc. (Con Edison) to grant permanent and temporary easements to Millwood Fire District (District) over a portion of the rear of Millwood Road (NY State Route 133), District Tax Map ID No. 81.09-3-1, Town of New Castle, Westchester County, New York. The proposed permanent easement would be 20’ wide by 595’ long (12,107± sq. ft.) over a portion of Con Edison’s real property (totaling approximately 32.8 acres) with overhead power transmission lines and towers. The permanent easement granted to the Millwood Fire District would be used by the District to construct a sub-surface drainage culvert to serve a new fire station that will be developed. In addition, Con Edison would also grant a temporary easement to the District for construction purposes.
Text of proposed rule and any required statements and analyses may be obtained by filing a Document Request Form (F-96) located on our website http://www.dps.ny.gov/f96dir.htm. For questions, contact:
Leann Ayer, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: [email protected]
Data, views or arguments may be submitted to:
Jaclyn A. Brilling, Secretary, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 474-6530, email: [email protected]
Public comment will be received until:
45 days after publication of this notice.
Regulatory Impact Statement, Regulatory Flexibility Analysis, Rural Area Flexibility Analysis and Job Impact Statement
Statements and analyses are not submitted with this notice because the proposed rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(12-M-0480SP1)