Petition Regarding CDG Compensation

NY-ADR

4/8/20 N.Y. St. Reg. PSC-47-19-00013-A
NEW YORK STATE REGISTER
VOLUME XLII, ISSUE 14
April 08, 2020
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
NOTICE OF ADOPTION
 
I.D No. PSC-47-19-00013-A
Filing Date. Mar. 19, 2020
Effective Date. Mar. 19, 2020
Petition Regarding CDG Compensation
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On 3/19/20, the PSC adopted an order granting, in part, with modifications, New York State Energy Research and Development Authority's (NYSERDA) petition regarding compensation for Community Distributed Generation (CDG) projects.
Statutory authority:
Public Service Law, sections 5(1)(b), (2), 65(1), (2), (3), 66(2), (5) and 66-p
Subject:
Petition regarding CDG compensation.
Purpose:
To grant, in part, with modifications, NYSERDA's petition regarding CDG compensation.
Substance of final rule:
The Commission, on March 19, 2020, adopted an order granting, in part, with modifications, New York State Energy Research and Development Authority's (NYSERDA) petition regarding compensation for Community Distributed Generation (CDG) projects. New York State Electric & Gas Corporation (NYSEG), Niagara Mohawk Power Corporation d/b/a National Grid (National Grid), and Rochester Gas and Electric Corporation (RG&E) are directed to file, in conformance with the discussion in the body of the Order, tariff leaves implementing the modifications to the Value of Distributed Energy Resources policy and to the Value Stack in the order, on not less than 20 days’ notice to become effective on May 1, 2020. NYSEG, National Grid and RG&E shall reallocate capacity that had been allocated to cancelled projects to the new Community Credit Tranche 2 to maintain total cumulative Market Transition Credit (MTC) and Community Credit capacity of 318 MW in NYSEG, 620 MW in National Grid, and 150 in RG&E NYSEG, National Grid, and RG&E shall each continue to reallocate capacity in this way until the later of November 1, 2020, or the first month in which the Community Credit Tranche 2 is full and there are no project cancellations. NYSEG, National Grid and RG&E are directed to provide updates at least once per month to NYSERDA including the current capacity in each Tranche and a list of any projects that are eligible for Community Credit Tranche 2 but have not yet been allocated capacity, in the order that those projects met the milestone for being assigned to a Tranche, subject to the terms and conditions set forth in the order.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
John Pitucci, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: [email protected] An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(15-E-0751SA30)
End of Document