Petition for Clarification

NY-ADR

4/7/21 N.Y. St. Reg. PSC-52-20-00005-A
NEW YORK STATE REGISTER
VOLUME XLIII, ISSUE 14
April 07, 2021
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
NOTICE OF ADOPTION
 
I.D No. PSC-52-20-00005-A
Filing Date. Mar. 19, 2021
Effective Date. Mar. 19, 2021
Petition for Clarification
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On 3/18/21, the PSC adopted an order approving Niagara Mohawk Power Corporation d/b/a National Grid's (National Grid) petition for clarification of Green Button Connect (GBC) implementation within the Advanced Metering Infrastructure (AMI) Order.
Statutory authority:
Public Service Law, sections 5, 65 and 66
Subject:
Petition for clarification.
Purpose:
To approve National Grid's petition for clarification of GCB implementation within the AMI Order.
Substance of final rule:
The Commission, on March 18, 2021, adopted an order approving Niagara Mohawk Power Corporation d/b/a National Grid's (National Grid) petition for clarification of Green Button Connect (GBC) implementation within the November 20, 2020 Order Authorizing Implementation of Advanced Metering Infrastructure with Modifications (AMI Order). National Grid shall continue to implement GBC by March 31, 2021, subject to the terms and conditions set forth in the order.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
John Pitucci, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: [email protected] An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(17-E-0238SA11)
End of Document