Amendments to the SIR

NY-ADR

11/18/20 N.Y. St. Reg. PSC-46-20-00006-P
NEW YORK STATE REGISTER
VOLUME XLII, ISSUE 46
November 18, 2020
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
PROPOSED RULE MAKING
NO HEARING(S) SCHEDULED
 
I.D No. PSC-46-20-00006-P
Amendments to the SIR
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following proposed rule:
Proposed Action:
The Commission is considering a petition filed by members of the Interconnection Policy Working Group requesting that the Commission amend the cost-sharing process in the New York State Standardized Interconnection Requirements (SIR).
Statutory authority:
Public Service Law, sections 5(1), (2), 65(1), (2), (3), 66(1), (2), (3), (5), (8) and (10)
Subject:
Amendments to the SIR.
Purpose:
To more effectively interconnect distributed generation and energy storage Systems 5 MW or less to the distribution system.
Substance of proposed rule:
The New York State Public Service Commission (Commission) is considering a petition filed on October 29, 2020 by members of the Interconnection Policy Working Group (IPWG) including, Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New York, Inc., New York State Electric & Gas Corporation, Niagara Mohawk Power Corporation d/b/a National Grid, Orange and Rockland Utilities, Inc., and Rochester Gas and Electric Corporation (collectively, the “Joint Utilities”) and the New York Solar Energy Industries Association (“NYSEIA”), New York Battery and Energy Storage Technology Consortium (“NY-BEST”), BQ Energy, LLC, Borrego Solar Systems, Inc., Cypress Creek Renewables, LLC, CleanChoice Energy, Oya Solar Inc., SunCommon, GreenSpark Solar, Distributed Sun, LLC, Clearway Energy Group LLC, Sol Systems, Omni Navitas, Ameresco, Nexamp, Inc., Blueprint Power, US Light Energy, Delaware River Solar, Dynamic Energy, EDF Renewables North America, NextEra Energy Resources, LLC, Novis Renewables, LLC, Con Edison Clean Energy Businesses, Inc., Boralex Inc., GEM Energy, East Light Partners, Horizon Power, Dimension Energy LLC, ETM Solar Works, Ric Energy, AES Distributed Energy, and Summit Ridge Energy (collectively, the IPWG Members).
The IPWG Members request that the Commission modify the “New York State Standardized Interconnection Requirements and Application Process For New Distributed Generators and Energy Storage Systems 5 MW or Less Connected in Parallel with Utility Distribution Systems” (the SIR), by replacing the current “first-mover” cost-sharing mechanism with the proposed “pro rata” cost sharing mechanism (the Cost-Sharing Proposal). The IPWG Members explain that the Cost-Sharing Proposal would equitably allocate the cost of distribution system upgrades by the utility assigning each interconnecting project a specific distribution hosting capacity fee when an upgrade is needed. The IPWG Members further explain that the Cost-Sharing Proposal applies to two categories of distribution upgrades: 1) “utility-initiated distributed generation (DG) or energy storage system (ESS) upgrades;” and, 2) “market-initiated DG/ESS upgrades.”
The proposed utility-initiated DG/ESS upgrade process would apply to each utility’s Capital Investment Plan (CIP), and will consider options to upgrade the equipment to provide for greater hosting capacity rather than a replacement-in-kind. This process would be initiated by each of the Joint Utilities posting a list of substations with major upgrade plans, or “multi-value distribution (MVD) plans,” on their respective system data portals and an estimate of funding needed to create additional hosting capacity to allow DG/ESS interconnections at that substation. This list will include an estimate of the financial obligation of a first-mover interconnection project and projects that may interconnect after the first project.
The proposed market-initiated DG/ESS upgrades process would occur when a hosting capacity upgrade is needed, there are at least two projects requesting interconnection at this site, and the CIP does not contemplate upgrading or replacing that equipment. Each utility would determine the interconnection fee in dollars per kilowatt (kW) by dividing the sum of the total costs of the “qualifying upgrade” at each designated location by a factor representing the sum of the total hosting capacity in kW of that designated location. The IPWG Members propose that costs of these qualifying upgrades not recovered by additional interconnecting projects sharing in the cost would be deferred until the utility’s next rate plan period for rate base recovery. To limit these potential unrecovered costs, the IPWG Members propose a cap of no more than two percent of a utility’s distribution/sub-transmission electric capital investment budget per fiscal year. The cap would be updated annually and calculated as a rolling five-year average of each utility’s forecasted distribution/sub-transmission electric capital investment for the impacted year and the next four years according to each utility’s current CIP. If this two percent cap is reached, the interconnecting projects would be required to fully fund any qualifying upgrades.
The IPWG Members propose that when a utility is planning a capital upgrade, the utility would create a “Capital Project Queue” at the substation or feeder level for those DG/ESS applications unable to interconnect due to the pending upgrade and update the hosting capacity map to reflect zero hosting capacity for that location. Projects already in the interconnection queue at that location may consent to join the Capital Project Queue or the utility will withdraw their interconnection application from the interconnection queue. SIR timelines would be suspended for projects in the Capital Project Queue until the upgrade is within 18 months of the expected completion date, at which time the projects would advance through the remaining SIR steps.
The IPWG Members propose that, if the Commission adopts this Cost-Sharing Proposal, interconnection applications in the queue should be treated in the following ways: (1) for interconnection applications that have not yet advanced to the Coordinated Electric System Interconnection Review (CESIR) process, the Cost-Sharing Proposal would apply; (2) for interconnection applications in the CESIR process, the Cost-Sharing Proposal would apply; (3) for interconnection applications that have completed the CESIR process, regardless of whether the initial 25 percent payment has been made or not, the interconnecting customer can request an evaluation of the completed CESIR to determine the applicability of the Cost-Sharing Proposal mechanism,; and (4) for interconnection applications that have made full payment, the interconnecting customer would not be eligible for the Cost-Sharing Proposal.
The full text of the petition and the full record of the proceeding may be reviewed online at the Department of Public Service web page: www.dps.ny.gov. The Commission may adopt, reject or modify, in whole or in part, the action proposed and may resolve related matters.
Text of proposed rule and any required statements and analyses may be obtained by filing a Document Request Form (F-96) located on our website http://www.dps.ny.gov/f96dir.htm. For questions, contact:
John Pitucci, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: [email protected]
Data, views or arguments may be submitted to:
Michelle L. Phillips, Secretary, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 474-6530, email: [email protected]
Public comment will be received until:
60 days after publication of this notice.
Regulatory Impact Statement, Regulatory Flexibility Analysis, Rural Area Flexibility Analysis and Job Impact Statement
Statements and analyses are not submitted with this notice because the proposed rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(20-E-0543SP1)
End of Document