SIR Modifications

NY-ADR

12/31/19 N.Y. St. Reg. PSC-39-19-00015-A
NEW YORK STATE REGISTER
VOLUME XLI, ISSUE 53
December 31, 2019
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
NOTICE OF ADOPTION
 
I.D No. PSC-39-19-00015-A
Filing Date. Dec. 13, 2019
Effective Date. Dec. 13, 2019
SIR Modifications
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On 12/12/19, the PSC adopted an order approving modifications to the New York State Standardized Interconnection Requirements (SIR).
Statutory authority:
Public Service Law, sections 65(1), (2), (3), 66(1), (2), (3), (5), (8) and (10)
Subject:
SIR modifications.
Purpose:
To approve modifications to the SIR.
Substance of final rule:
The Commission, on December 12, 2019, adopted an order approving modifications to the New York State Standardized Interconnection Requirements (SIR), filed in a petition by Central Hudson Gas & Electric Corporation (Central Hudson), Consolidated Edison Company of New York, Inc. (Con Edison), New York State Electric & Gas Corporation (NYSEG), Niagara Mohawk Power Corporation d/b/a National Grid (National Grid), Orange and Rockland Utilities, Inc. (O&R), Rochester Gas and Electric Corporation (RG&E), the New York Solar Energy Industries Association, New York Battery and Energy Storage Technology Consortium, BQ Energy, LLC, Clean Energy Collective, Monolith Solar Associates, Cypress Creek Renewables, Borrego Solar Systems, Inc., CleanChoice Energy, Oya Solar Inc., SunCommon, GreenSpark Solar, EnterSolar, Distributed Sun, LLC, Clearway Energy Group LLC, Safari Energy, LLC, Sol Systems, Omni Navitas, Ameresco, Nexamp, Inc., Blueprint Power, US Light Energy, Best Energy Power, Delaware River Solar, Dynamic Energy, EDF Renewables North America, and Sunrun Inc.; members of the Interconnection Policy Working Group (IPWG) and the Interconnection Technical Working Group (ITWG). Central Hudson, Con Edison, NYSEG, National Grid, O&R and RG&E are directed to make tariff filings to incorporate into their electric tariffs the revised SIR set forth in Appendix A, and to remove any inconsistent tariff provisions. These tariff amendments shall become effective on not less than one day’s notice, to take effect on or before January 1, 2020, subject to the terms and conditions set forth in the order.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
John Pitucci, Public Service Commission, 3 Empire State Plaza, Albany, New York 12223-1350, (518) 486-2655, email: [email protected] An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(19-E-0566SA1)