Provisions for Reactive Demand

NY-ADR

7/6/11 N.Y. St. Reg. PSC-15-11-00019-A
NEW YORK STATE REGISTER
VOLUME XXXIII, ISSUE 27
July 06, 2011
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
NOTICE OF ADOPTION
 
I.D No. PSC-15-11-00019-A
Filing Date. Jun. 16, 2011
Effective Date. Jun. 16, 2011
Provisions for Reactive Demand
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On 6/16/11, the PSC adopted an order approving the Central Hudson Gas & Electric's amendments to PSC No. 15—Electricity, effective July 1, 2011, proposing to clarify the provisions for reactive demand applicable to customers operating on-site induction.
Statutory authority:
Public Service Law, section 66(12)
Subject:
Provisions for Reactive Demand.
Purpose:
To approve Central Hudson Gas & Electric's amendments to PSC No. 15—Electricity, effective 7/1/11.
Substance of final rule:
The Commission, on June 16, 2011 adopted an order approving the Central Hudson Gas & Electric's amendments to PSC No. 15—Electricity, effective July 1, 2011, proposing to clarify the provisions for reactive demand applicable to customers operating on-site induction generators to more explicitly state how the reactive demand is calculated.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
Leann Ayer, Public Service Commission, Three Empire State Plaza, Albany, New York 12223, (518) 486-2655, email: [email protected] An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(11-E-0109SA1)