Implementation of Outage Recommendations
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
On July 16, 2008, the Public Service Commission adopted an order denying the petitions for rehearing by the City of New York and the Consumer Protection Board and granted Consolidated Edison Company of New York, Inc.'s request for an extension of its budget modification deadline.
Statutory authority:
Public Service Law, sections 4(1), 5(1), 22, 66(1), (2) and (4)
Subject:
Implementation of outage recommendations.
Purpose:
To deny the petitions for rehearing and grant an extension for budget modifications.
Substance of final rule:
The Commission, on July 16, 2008, adopted an order, denying the petitions for rehearing filed by the City of New York and the Consumer Protection Board and granted Consolidated Edison Company of New York, Inc.'s request for an extension of its budget modification deadline, subject to the terms and conditions set forth in the order.
Final rule as compared with last published rule:
No changes.
Text of rule may be obtained from:
Leann Ayer, Public Service Commission, Three Empire State Plaza, Albany, NY 12223, (518) 486-2655, e-mail: [email protected]
Assessment of Public Comment:
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.
(06-E-0894SA7)
End of Document