Transfer of Ownership of a Gas Fired Electric Generation Facility by Rensselaer Cogeneration LL...

NY-ADR

6/6/07 N.Y. St. Reg. PSC-13-07-00014-A
NEW YORK STATE REGISTER
VOLUME XXIX, ISSUE 23
June 06, 2007
RULE MAKING ACTIVITIES
PUBLIC SERVICE COMMISSION
NOTICE OF ADOPTION
 
I.D No. PSC-13-07-00014-A
Filing Date. May. 21, 2007
Effective Date. May. 21, 2007
Transfer of Ownership of a Gas Fired Electric Generation Facility by Rensselaer Cogeneration LLC, et al.
PURSUANT TO THE PROVISIONS OF THE State Administrative Procedure Act, NOTICE is hereby given of the following action:
Action taken:
The commission, on May 16, 2007, adopted an order approving the petition of Rensselaer Cogeneration LLC, Bison Power LLC, and Rensselaer Holdings LLC for the transfer of ownership interests in a 79.4 MW natural gas fired electric generation facility located in Rensselaer, NY and lightened regulation for the facility.
Statutory authority:
Public Service Law, sections 2(13), 5(1)(b), 64, 65, 66, 67, 68, 69, 69-a, 70, 71, 72, 72-a, 75, 105, 106, 107, 108, 109, 110, 111, 112, 113, 114, 114-a, 115, 117, 118, 119-b and 119-c
Subject:
Transfer of ownership and lightened regulation of an approximately 79 MW gas fired electric generation facility.
Purpose:
To approve the transfer of ownership and lightened regulation of an approximately 79 MW gas fired electric generation facility.
Substance of final rule:
The Commission adopted an order approving the Petition of Rensselaer Cogeneration LLC, Bison Power LLC, and Rensselaer Holdings LLC for the transfer of ownership interests in a 79.4 MW natural gas fired electric generation facility located in Rensselaer, New York and lightened regulation for the facility, subject to the terms and conditions of the order.
Final rule compared with proposed rule:
No changes.
Text of rule may be obtained from:
Central Operations, Public Service Commission, Bldg. 3, 14th Fl., Empire State Plaza, Albany, NY 12223-1350, by fax to (518) 474-9842, by calling (518) 474-2500. An IRS employer ID no. or social security no. is required from firms or persons to be billed 25 cents per page. Please use tracking number found on last line of notice in requests.
Assessment of Public Comment
An assessment of public comment is not submitted with this notice because the rule is within the definition contained in section 102(2)(a)(ii) of the State Administrative Procedure Act.