§ 1322. Outages of electric generating units
Purdon's Pennsylvania Statutes and Consolidated StatutesTitle 66 Pa.C.S.A. Public Utilities
66 Pa.C.S.A. § 1322
§ 1322. Outages of electric generating units
(a) General rule.--Whenever an electric generating unit, determined by the commission to be a base load unit, is out of service for more than 120 consecutive days, a utility owning a share of that unit shall not be permitted to recover, through base rates, a sliding scale of rates, or by any other means, the excess energy costs incurred to generate or purchase replacement power occasioned by any portion of the outage which the commission determines to be unreasonable or imprudent. In making its determination under this subsection, the commission shall consider, in addition to any other relevant evidence, whether the outage could have been shortened or avoided if the unit had been properly constructed, operated or maintained.
(b) Notice of outage.--Whenever an electric generating unit, determined by the commission to be a base load unit, is out of service for 45 consecutive days, any utility owning a share of that unit shall submit to the commission and the Office of Consumer Advocate a status report on that outage. The utility shall submit subsequent status reports on the outage to the commission and the Office of Consumer Advocate at least by the 20th day of each subsequent month until the unit returns to service. If more than one utility owns a share in the electric generating unit, the commission may designate one utility to make the reports required by this subsection.
(c) Operation at less than reasonable level of generation.--Whenever the actual generation of an electric generating unit, determined by the commission to be a base load unit, is less than 50% of the unit's potential generation during any calendar year or other 12-month period specified by the commission, the commission, on its own motion or upon complaint, may initiate an investigation to determine a reasonable level of generation for that unit. In establishing rates as part of that investigation or in any subsequent proceeding, the commission shall not permit recovery of the excess energy costs incurred to generate or purchase replacement power occasioned by the failure of the unit to operate at or above such reasonable level of generation, if such failure is determined to be unreasonable or imprudent.
Credits
1986, July 10, P.L. 1238, No. 114, § 9, imd. effective.