§ 26-2602-J. School construction and renovation approval process
Purdon's Pennsylvania Statutes and Consolidated StatutesTitle 24 P.S. EducationEffective: July 1, 2020
Effective: July 1, 2020
24 P.S. § 26-2602-J
§ 26-2602-J. School construction and renovation approval process
(a) General rule.--To be eligible to receive reimbursement from the Commonwealth for costs of a project, a school entity must receive appropriate approval from the department. To be eligible to receive approval, a school entity shall comply with the following process as developed and administered by the department in the order prescribed under this section:
(F) Preliminary materials required under section 701.1.1
(D) An application for reimbursement for the project under section 2606-J.2
Credits
1949, March 10, P.L. 30, No. 14, art. XXVI-J, § 2602-J, added 2019, July 2, P.L. 417, No. 70, § 1.
24 P.S. § 26-2602-J, PA ST 24 P.S. § 26-2602-J