§ 8903-H. Application and plan
Purdon's Pennsylvania Statutes and Consolidated StatutesTitle 72 P.S. Taxation and Fiscal AffairsEffective: July 8, 2022
Effective: July 8, 2022
72 P.S. § 8903-H
§ 8903-H. Application and plan
<Section 24(4)(xiv) of Act 2022, July 8, P.L. 513, No. 53, provides that the addition of this section by that Act shall apply to fiscal years beginning after June 30, 2022.>
(c) Approval of plan.--Upon receipt of a plan submitted by an airport under subsection (b), the department shall have 60 calendar days to review the plan for appropriateness and conformity. If the proposed plan conforms with this article, the department shall approve the plan. If the proposed plan does not conform, the department shall notify the applicant in writing. The airport may revise the plan to make the plan conform with this article. Upon receipt of the revised plan, the department shall have 60 days to approve the revised plan.
(f) Change.--An airport may change the approved plan by subdividing a parcel, changing the legal description of a parcel, moving the zone designation to another qualifying parcel owned by an airport or making physical changes to a vacant building in the zone by adding to the building's size or reducing the building's size after the plan has been approved. If an airport chooses to make the changes, the airport shall notify the department and the Department of Revenue of the changes. The department shall issue a document confirming the changes to the airport's zone.
Credits
1971, March 4, P.L. 6, No. 2, art. XIX-H, § 1903-H, added 2022, July 8, P.L. 513, No. 53, § 15, imd. effective.
72 P.S. § 8903-H, PA ST 72 P.S. § 8903-H
Current through Act 10 of the 2024 Regular Session. Some statute sections may be more current, see credits for details.
End of Document |