§ 1396.18j. Construction of act
Purdon's Pennsylvania Statutes and Consolidated StatutesTitle 52 P.S. Mines and Mining
52 P.S. § 1396.18j
§ 1396.18j. Construction of act
Any provisions to the contrary notwithstanding, it shall be the intent of the General Assembly, and this act shall not be construed to violate any of the requirements of the Clean Water Act of 1977 (Public Law 95-217, 33 U.S.C. § 1251 et seq.) and the Surface Mining Control and Reclamation Act of 1977 (Public Law 95-87, 30 U.S.C. § 1201, et seq.).
Credits
1945, May 31, P.L. 1198, § 18.10, added 1992, Dec. 18, P.L. 1384, No. 173, § 11, effective in 60 days.
52 P.S. § 1396.18j, PA ST 52 P.S. § 1396.18j
Current through Act 10 of the 2024 Regular Session. Some statute sections may be more current, see credits for details.