Home Table of Contents

§ 1396.3b. Specifications for construction projects

Purdon's Pennsylvania Statutes and Consolidated StatutesTitle 52 P.S. Mines and Mining

Purdon's Pennsylvania Statutes and Consolidated Statutes
Title 52 P.S. Mines and Mining (Refs & Annos)
Chapter 15. Surface Mining Conservation and Reclamation Act (Refs & Annos)
52 P.S. § 1396.3b
§ 1396.3b. Specifications for construction projects
It shall be the duty of architects, engineers, or other persons preparing specifications for construction projects and which specifications include the requirement that the construction contractor supply fill for such project, to include within such specifications a specific reference to this act and the regulations pertaining thereto adopted by the department. If such a reference is omitted from the specifications and reclamation and planting of the land from which the fill was removed by the construction contractor is required under this act, any contract based on such specifications may be amended, at the option of the construction contractor, to allow a reasonable price for the reclamation and planting of the land affected in accordance with a plan acceptable to the secretary.

Credits

1945, May 31, P.L. 1198, § 3.2, added 1971, Nov. 30, P.L. 554, No. 147, § 4. Amended 1980, Oct. 10, P.L. 835, No. 155, § 4, imd. effective.
52 P.S. § 1396.3b, PA ST 52 P.S. § 1396.3b
Current through Act 10 of the 2024 Regular Session. Some statute sections may be more current, see credits for details.
End of Document