§ 5536. Construction projects
Purdon's Pennsylvania Statutes and Consolidated StatutesTitle 42 Pa.C.S.A. Judiciary and Judicial Procedure
42 Pa.C.S.A. § 5536
§ 5536. Construction projects
(a) General rule.--Except as provided in subsection (b), a civil action or proceeding brought against any person lawfully performing or furnishing the design, planning, supervision or observation of construction, or construction of any improvement to real property must be commenced within 12 years after completion of construction of such improvement to recover damages for:
(1) If an injury or wrongful death shall occur more than ten and within 12 years after completion of the improvement a civil action or proceeding within the scope of subsection (a) may be commenced within the time otherwise limited by this subchapter, but not later than 14 years after completion of construction of such improvement.
(2) The limitation prescribed by subsection (a) shall not be asserted by way of defense by any person in actual possession or control, as owner, tenant or otherwise, of such an improvement at the time any deficiency in such an improvement constitutes the proximate cause of the injury or wrongful death for which it is proposed to commence an action or proceeding.
Credits
1976, July 9, P.L. 586, No. 142, § 2, effective June 27, 1978. Amended 1978, April 28, P.L. 202, No. 53, § 10(63.1), effective June 27, 1978.
42 Pa.C.S.A. § 5536, PA ST 42 Pa.C.S.A. § 5536
Current through Act 10 of the 2024 Regular Session. Some statute sections may be more current, see credits for details.