255.1009 Required report when compression couplings fail.
(a) Except as provided in subdivision (b) of this section, each operator of a distribution pipeline system must submit a report on each mechanical fitting failure, excluding any failure that results only in a nonhazardous leak, on a Department of Transportation form PHMSA F-7100.1-2. The report(s) must be submitted in accordance with 49 CFR 191.12.
(b) The mechanical fitting failure reporting requirements in subdivision (a) of this section do not apply to the following:
(1) master meter operators;
(2) small LPG operator as defined in section 255.1001 of this Part; or
(3) LNG facilities.