1002.12 Capital construction contracts.
(a) The ROI date shall be adjusted whenever, in the case of any payments on capital construction contracts, the corporation's project manager or chief engineer or their designee determines that the contractor has failed to properly submit the necessary documents and other materials prescribed by or provided for in the contract specifications, terms and conditions, or requirements, or by any applicable local, State and Federal law or regulation, in order to enable the corporation to process the payment properly and expeditiously.
(b) The corporation's project manager or chief engineer or their designee shall send written notice to the contractor of his failure to submit the necessary documents and materials. The notice shall indicate all documents and materials required.
(c) The ROI date shall be the original ROI date increased by the number of days beginning on the date that the corporation's project manager or chief engineer or their designee sends written notice to the contractor of his failure to submit the necessary documents and materials and ending on the date that the corporation receives the necessary documents and materials.
21 CRR-NY 1002.12
Current through July 15, 2021
End of Document

IMPORTANT NOTE REGARDING CONTENT CURRENCY: JULY 31, 2023, is the date of the most recently produced official NYCRR supplement covering this rule section. For later updates to this section, if any, please: consult editions of the NYS Register published after this date; or contact the NYS Department of State Division of Admisnistrative Rules at [email protected]. See Help for additional information on the currency of this unofficial version of the NYS Rules.