504.5 Exceptions and extension of payment due date.
The authority has determined that, notwithstanding the provisions of sections 504.3 and 504.4 of this Part, any of the following facts or circumstances, which may occur concurrently or consecutively, reasonably justify extension of the payment due date.
(a) If the case of a payment which a contract provides will be made on a specific date or at a predetermined interval, without having to submit a written invoice, if any documentation, supporting data, performance verification, or notice specifically required by the contract or other State or Federal mandate has not been submitted to the authority on a timely basis, then the payment due date shall be extended by the number of calendar days from the date by which all such matter was to be submitted to the authority and the date when the authority has actually received such matter.
(b) If an inspection or testing period, performance verification, audit or other review or documentation independent of the contractor is specifically required by the contract or by other State or Federal mandate, whether to be performed by or on behalf of the authority or another entity, or is specifically permitted by the contract or by other State or Federal provision and the authority or other entity with the right to do so elects to have such activity or documentation undertaken, then the payment due date shall be extended by the number of calendar days from the date of receipt of an invoice to the date when any such activity or documentation has been completed, the authority has actually received the results of such activity or documentation conducted by another entity, and any deficiencies identified or issues raised as a result of such activity or documentation have been corrected or otherwise resolved.
(c) If an invoice must be examined by a State or Federal agency, or by another party contributing to the funding of the contract, prior to payment, then the payment due date shall be extended by the number of calendar days from the date of receipt of an invoice to the date when the State or Federal agency, or other contributing party to the contract, has completed the inspection, advised the authority of the results of the inspection, and any deficiencies identified or issues raised as a result of such inspection have been corrected or otherwise resolved.
(d) If appropriated funds from which payment is to be made have not yet been appropriated or, if appropriated, not yet been made available to the authority, then the payment due date shall be extended by the number of calendar days from the date of receipt of an invoice to the date when such funds are made available to the authority.