16 CRR-NY 88.4NY-CRR

STATE COMPILATION OF CODES, RULES AND REGULATIONS OF THE STATE OF NEW YORK
TITLE 16. DEPARTMENT OF PUBLIC SERVICE
CHAPTER I. RULES OF PROCEDURE
SUBCHAPTER G. CERTIFICATES OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED
PART 88. EXHIBITS FOR ELECTRIC TRANSMISSION FILINGS
16 CRR-NY 88.4
16 CRR-NY 88.4
88.4 Exhibit E-4: engineering justification.
(a) The applicant shall:
(1) provide the engineering justification for the proposed transmission line, showing its relation to the existing facilities of the applicant and the interconnected network;
(2) indicate specific benefits with respect to reliability and economy to the applicant and the interconnected network;
(3) state the proposed date for completion of the line and indicate the impact on the systems of the applicant and others of failure to complete the proposed transmission line on such date; and
(4) provide appropriate system studies, showing expected flows on the line under normal, peak and emergency conditions, including the system reliability impact study forwarded by the Transmission Planning Advisory Subcommittee for approval by the operating committee of the New York Independent System Operator, which shows effects on stability of the interconnected system.
16 CRR-NY 88.4
Current through February 28, 2023
End of Document

IMPORTANT NOTE REGARDING CONTENT CURRENCY: JULY 31, 2023, is the date of the most recently produced official NYCRR supplement covering this rule section. For later updates to this section, if any, please: consult editions of the NYS Register published after this date; or contact the NYS Department of State Division of Admisnistrative Rules at [email protected]. See Help for additional information on the currency of this unofficial version of the NYS Rules.