85-1.4 Determination of line length and system configuration.
(a) In calculating the length of a line to determine whether an application or NOI should be filed:
(1) the length of a well line shall be measured from the trap or separator at the well to the point at which the gas being transported from the well commingles with other gas; and
(2) the length of any other line shall be measured from the point at which gas leaves one pipeline to the point at which it enters another pipeline.
(b) Any NOI or application shall include every line then planned for a proposed system. A system includes all lines tying into a common point leading to market, which is usually a meter site, but may be a regulator station or compressor site. The type of document submitted will be determined by the length of the longest line included.15

Footnotes

15
The document filed should include a map showing all lines anticipated to be part of a given system, even though not proposed for construction at the time of the current filing.