255.329 Installation of plastic pipelines by trenchless excavation.
Plastic pipelines installed by trenchless excavation must comply with the following:
(a) Each operator must take practicable steps to provide sufficient clearance for installation and maintenance activities from other underground utilities and/or structures at the time of installations.
(b) For each pipeline section, plastic pipe and components that are pulled through the ground must use a weak link, as defined by section 255.3 of this Part, to ensure the pipeline will not be damaged by any excessive forces during the pulling process.
16 CRR-NY 255.329
Current through March 31, 2022
End of Document

IMPORTANT NOTE REGARDING CONTENT CURRENCY: JULY 31, 2023, is the date of the most recently produced official NYCRR supplement covering this rule section. For later updates to this section, if any, please: consult editions of the NYS Register published after this date; or contact the NYS Department of State Division of Admisnistrative Rules at [email protected]. See Help for additional information on the currency of this unofficial version of the NYS Rules.