12 CRR-NY 14-1.11NY-CRR

STATE COMPILATION OF CODES, RULES AND REGULATIONS OF THE STATE OF NEW YORK
TITLE 12. DEPARTMENT OF LABOR
CHAPTER I. INDUSTRIAL BOARD OF APPEALS
SUBCHAPTER A. THE INDUSTRIAL CODE
PART 14. CONSTRUCTION, INSTALLATION, INSPECTION AND MAINTENANCE OF HIGH PRESSURE BOILERS; CONSTRUCTION OF UNFIRED PRESSURE VESSELS
SUBPART 14-1. DEFINITIONS
12 CRR-NY 14-1.11
12 CRR-NY 14-1.11
14-1.11 Electrical steam generators.
All electrical steam generators shall be installed in accordance with the requirements of the ASME Code.
12 CRR-NY 14-1.11
Current through March 15, 2022
End of Document