71.13 General conditions of program assistance.
(a) Use of loan proceeds.
The program recipient must use the loan proceeds to finance the implementation of the wastewater treatment project approved by the department.
(b) Completion of work.
Work on wastewater treatment projects which receive program assistance must be completed within one year after the loan closing. The department may extend this period on a case-by-case basis where the program recipient has demonstrated reasonable cause for the delay.
(c) Certificate of completion.
Within 45 days of completion of the project, the program recipient must provide the department with a certificate of completion, signed by the program recipient and the contractor, certifying that the wastewater treatment project was completed in accordance with the descriptions and cost estimates provided to the department.
(d) Changes in scope of work.
The program recipient shall promptly provide written notice to the department of any necessary changes in a wastewater treatment project which differ from the program application submitted to the department, and no such change in the scope of work shall occur unless approved in writing by the department.
(e) Change in project cost.
The program recipient shall promptly provide written notice to the department of any change in the cost of a wastewater treatment project which differs by either more than 10 percent or $20,000 from the selected contractor's cost estimate, or the program recipient's schedules and selected estimate in the case of an in-house project, submitted to the department, and a justification therefor. No such change in project costs shall occur unless approved in writing by the department; provided, however, that under no circumstances will program assistance be available for an amount exceeding the cost of the project.
(f) Site inspection.
The program recipient must provide the department, or its designated agents, with reasonable access to the project site before, during, and after the construction phase of the wastewater treatment project in order to monitor and inspect the work being undertaken with program assistance.
(g) Applicable laws and permits.
The program recipient must perform all work in compliance with all applicable Federal, State, and local laws, rules and regulations. Prior to the commencement of work, the program recipient must obtain all permits, certificates and approvals which may be required in connection with the performance and completion of the work.
(h) Documentation of work.
The program recipient must retain for a period of six years after the date of closing on the loan all cancelled checks, receipts and contracts used in connection with the work on the wastewater treatment project, and must produce them at the request of the department for the purpose of verifying the cost of the project.
(i) Reporting.
On each anniversary date of the loan closing during the term of program assistance, the program recipient shall submit to the department a copy of the applicant's most recent fiscal year end financial statement and an assessment, based on generally accepted engineering standards and practices, of energy cost savings achieved during the preceding year as a result of the wastewater treatment project.
(j) Reimbursement for failure to comply.
If the program recipient fails to comply with the requirements of this Part, the program recipient may be disqualified from participating in the program, program assistance may be rescinded, and the applicant may be required to reimburse the department for all or a portion of the program assistance which the department has advanced.