§ 4-209. Allocation of costs of relocating utilities underground
West's Annotated Code of MarylandPublic UtilitiesEffective: October 1, 2012
Effective: October 1, 2012
MD Code, Public Utilities, § 4-209
Formerly cited as MD PUBLIC UTIL COMP § 4-209
§ 4-209. Allocation of costs of relocating utilities underground
(a) With respect to the net capital costs associated with the relocation underground of utility lines and facilities in connection with projects required by § 8-401 of the Land Use Article, the Commission shall:
(b) A utility may not be required to pay more than 50% of the net capital costs of a relocation project.
Credits
Added by Acts 1998, c. 8, § 2, eff. Oct. 1, 1998. Amended by Acts 2012, c. 427, § 1, eff. Oct. 1, 2012.
Formerly Art. 78, § 72A.
MD Code, Public Utilities, § 4-209, MD PUBLIC UTIL § 4-209
Current through legislation effective through July 1, 2024, from the 2024 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.
End of Document |