§ 7-306.1. Application for interconnection of solar electric generation facility during certain...
West's Annotated Code of MarylandPublic UtilitiesEffective: October 1, 2016
Effective: October 1, 2016
MD Code, Public Utilities, § 7-306.1
§ 7-306.1. Application for interconnection of solar electric generation facility during certain negotiations with eligible customer-generator
(a) A person who is negotiating a contract with an eligible customer-generator to install a solar electric generating facility on the customer-generator's property that the customer-generator owns and operates, leases and operates, or contracts with a third party that owns and operates and that requires interconnection with an electric company's distribution facilities:
(b) On request of a person under subsection (a)(1) of this section, an electric company shall process an application submitted under subsection (a)(1) of this section and notify the person whether the application is approved or disapproved in accordance with a process and time frame specified in regulations adopted by the Commission.
(c)(1) In this subsection, “installation process” includes:
(2)(i) Subject to subparagraph (ii) of this paragraph, an electric company shall issue acceptance and final approval to operate a customer-generator's solar electric generating facility on the electric company's distribution facilities within 20 business days after the completion of the installation process and receipt of the paperwork and documentation set forth in paragraph (1)(iii) of this subsection.
Credits
Added by Acts 2015, c. 161, § 1, eff. Oct. 1, 2015. Amended by Acts 2016, c. 430, § 1, eff. Oct. 1, 2016; Acts 2016, c. 431, § 1, eff. Oct. 1, 2016.
MD Code, Public Utilities, § 7-306.1, MD PUBLIC UTIL § 7-306.1