§ 2-405. Public Service Commission hearings
West's Annotated Code of MarylandEnvironmentEffective: October 1, 2021
Effective: October 1, 2021
MD Code, Environment, § 2-405
§ 2-405. Public Service Commission hearings
(a)(1)(i) Whenever the Public Service Commission notifies the Secretary of an application for a certificate of public convenience and necessity under § 7-207 of the Public Utilities Article, the Secretary shall prepare a recommendation in connection with the permit or registration required by this subtitle and the issues the Public Service Commission must consider under § 7-207 of the Public Utilities Article relating to climate change.
(3) If a person files an application for an operating permit under this subtitle simultaneously with an application for a certificate, the Department shall consolidate its procedures for the issuance of the operating permit with the Public Service Commission's proceedings for issuance of the certificate and shall issue the operating permit simultaneously with the certificate unless consolidation would be inconsistent with the procedures set forth in the federal Clean Air Act.1
(b) Subject to judicial review as provided under Title 3, Subtitle 2 of the Public Utilities Article, the decision of the Public Service Commission in connection with a certificate of public convenience and necessity or a filing under § 7-206 of the Public Utilities Article is binding on the Secretary.
(c) When a person that is required to obtain a certificate of public convenience and necessity applies for an operating permit for a generating station under this subtitle, the person shall send a copy of the application, at the time of filing, to the Public Service Commission.
(d) The Department shall consolidate procedures for the issuance of the operating permit with procedures of the Public Service Commission for the approval of the installation of pollution control equipment or a change in the method of operation unless consolidation would be inconsistent with the procedures set forth in the federal Clean Air Act.
(e)(1) Before issuing an operating permit which requires the installation of pollution control equipment or a change in the method of operation of the generating station or unit to any person required to obtain a certificate of public convenience and necessity, the Secretary shall notify the applicant and the Public Service Commission and request that the Public Service Commission institute a hearing as required by § 7-206 of the Public Utilities Article.
(f)(1) The Commission shall conduct the hearing required by subsection (e) of this section in the manner set forth in §§ 7-205 and 7-207 of the Public Utilities Article.
(g) Except as provided in subsection (h) of this section, the Secretary shall consult with the Public Service Commission concerning the impact of any operating permit, order or injunction on the supply and cost of electricity in this State before issuing any operating permit, issuing any order, or seeking any injunction under this subtitle that:
(h)(1) The Secretary need not consult with the Commission before issuing an order or seeking an injunction if the Secretary concludes that the delay during consultation could harm public health or the environment.
(i) The failure of the Department or the Public Service Commission to comply with this section is not a defense to an action against a person to enforce, to obtain, or to punish for noncompliance with any permit, certificate, order, or injunction.
Credits
Added by Acts 1982, c. 240, § 2. Amended by Acts 1983, c. 583, § 2; Acts 1986, c. 293, § 1; Acts 1992, c. 194; Acts 1998, c. 653, § 1, eff. Oct. 1, 1998; Acts 2001, c. 347, § 1, eff. July 1, 2001; Acts 2010, c. 52, § 1, eff. Oct. 1, 2010; Acts 2021, c. 614, § 1, eff. Oct. 1, 2021; Acts 2021, c. 615, § 1, eff. Oct. 1, 2021.
Formerly Art. 43, § 706.
Footnotes
42 U.S.C.A. § 7401 et seq.
MD Code, Environment, § 2-405, MD ENVIR § 2-405
Current through legislation effective through April 9, 2023, from the 2024 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.