§ 7-217. Electric school bus pilot program
West's Annotated Code of MarylandPublic UtilitiesEffective: June 1, 2022
Effective: June 1, 2022
MD Code, Public Utilities, § 7-217
§ 7-217. Electric school bus pilot program
(c) An investor-owned electric company may apply to the Commission to implement an electric school bus pilot program if the pilot program is structured to:
(7) provide for the selection of school systems that apply to participate in the pilot program on the basis of appropriate factors determined by the investor-owned electric company with the approval of the Commission, including the locational benefits that the storage batteries of school buses may bring to the investor-owned electric company;
(d) A participating school system shall:
(e) Subject to the Commission's approval, an investor-owned electric company may recover all reasonable and prudent program costs incurred under an electric school bus pilot program through a mechanism that is reviewed and approved by the Commission.
(f) Subject to the Commission's approval, an investor-owned electric company may establish a pilot tariff or rate to provide service to an electric school bus.
(g) An investor-owned electric company that applies to implement an electric school bus pilot program shall provide to the Commission any information, data, and analysis that the Commission requires.
(h) The Commission shall approve, deny, or approve with modifications an investor-owned electric company's application to implement an electric school bus pilot program.
(i)(1) An investor-owned electric company that establishes an electric school bus pilot program authorized by this section shall, in consultation with each participating school system, by February 1, 2025, and each year thereafter for the duration of the pilot program, report on the status of the pilot program to the Governor, the Commission, and, in accordance with § 2-1257 of the State Government Article, the House Economic Matters Committee and the Senate Finance Committee.
(j) The initial duration of an electric school bus pilot program shall be at least 3 years and may not exceed 5 years.
Credits
Added by Acts 2022, c. 38, § 4, eff. June 1, 2022; Acts 2022, c. 570, § 1, eff. June 1, 2022.
MD Code, Public Utilities, § 7-217, MD PUBLIC UTIL § 7-217
Current with all legislation from the 2023 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.
End of Document |