§ 4-205. State or federal construction
West's Annotated Code of MarylandEnvironmentEffective: October 1, 2013
Effective: October 1, 2013
MD Code, Environment, § 4-205
§ 4-205. State or federal construction
(a) The provisions of § 4-204 of this subtitle do not apply to the construction activities of State or federal agencies.
(b) After July 1, 1984, a State or federal agency may not undertake any land clearing, soil movement, or construction activity involving soil movement unless the agency has submitted and obtained approval of a stormwater management plan from the Department or the Department's designee.
(c)(1) On the request of a county or municipality, the Department or the Department's designee shall require that a State or federal agency submit a stormwater management plan to the requesting jurisdiction for review and comment, which review and comment shall be completed, returned, and received by the State or federal agency within 21 calendar days of receipt of the plan.
(2) The Department or the Department's designee shall require that the State or federal agency include the local jurisdictions' comments that are received within the time period required under paragraph (1) of this subsection as part of its stormwater management plan which is submitted for approval to the Department.
Credits
Added by Acts 1982, c. 682. Amended by 1985, c. 728; Acts 1987, c. 306, § 3; Acts 1989, c. 102; Acts 2013, c. 81, § 1, eff. Oct. 1, 2013.
MD Code, Environment, § 4-205, MD ENVIR § 4-205
Current with legislation effective through July 1, 2023, from the 2023 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.