§ 15-217. Submission of protest or contract claim

West's Annotated Code of MarylandState Finance and Procurement

West's Annotated Code of Maryland
State Finance and Procurement
Division II. General Procurement Law [Titles 11-End] (Refs & Annos)
Title 15. Procurement Contract Administration and Dispute Resolution (Refs & Annos)
Subtitle 2. Dispute Resolution (Refs & Annos)
Part III. Procedures for Dispute Resolution (Refs & Annos)
MD Code, State Finance and Procurement, § 15-217
§ 15-217. Submission of protest or contract claim
In general
(a)(1) A prospective bidder or offeror, a bidder, or an offeror may submit a protest to the procurement officer.
(2) A unit or a person who has been awarded a procurement contract may submit a contract claim to the procurement officer.
Time for submission
(b) Except as provided in § 15-219 of this subtitle, a protest or contract claim shall be submitted within the time required under regulations adopted by the primary procurement unit responsible for the procurement.

Credits

Added by Acts 1988, c. 48, § 2, eff. Oct. 1, 1988. Amended by Acts 1996, c. 682, § 1, eff. Oct. 1, 1996; Acts 2004, c. 373, § 1, eff. Oct. 1, 2004.
MD Code, State Finance and Procurement, § 15-217, MD STATE FIN & PROC § 15-217