Home Table of Contents

§ 5-1606. Forestation level requirements

West's Annotated Code of MarylandNatural ResourcesEffective: June 1, 2017 to June 30, 2024

West's Annotated Code of Maryland
Natural Resources
Title 5. Forests and Parks (Refs & Annos)
Subtitle 16. Forest Conservation (Refs & Annos)
Effective: June 1, 2017 to June 30, 2024
MD Code, Natural Resources, § 5-1606
§ 5-1606. Forestation level requirements
<Section effective until July 1, 2024. See, also, section 5-1606 effective July 1, 2024.>
Afforestation standards
(a)(1) For the following land use categories, tracts having less than 20% of the net tract area in forest cover shall be afforested up to 20% of the net tract area:
(i) Agriculture and resource areas; and
(ii) Medium density residential areas.
(2) For the following land use categories, tracts having less than 15% of the net tract area in forest cover shall be afforested up to 15% of the net tract area:
(i) Institutional development areas;
(ii) High density residential areas;
(iii) Mixed use and planned unit development areas; and
(iv) Commercial and industrial use areas.
(3) Afforestation requirements must conform to the conditions in §§ 5-1607 and 5-1610 of this subtitle, including payment into the Forest Conservation Fund, if afforestation on-site or off-site cannot be reasonably accomplished.
(4)(i) The afforestation requirements under this subsection shall be accomplished within 1 year or 2 growing seasons after the completion of the development project.
(ii) If afforestation cannot be reasonably accomplished on-site or off-site, the requirement to contribute money to a Forest Conservation Fund under § 5-1610 of this subtitle shall be met within 90 days after the completion of the development project.
(5) Linear projects that involve no change in land use may not be subject to afforestation requirements.
Forest conservation threshold
(b) There is a forest conservation threshold established for all land use categories as provided in subsection (c) of this section. The forest conservation threshold means the percentage of the net tract area at which the reforestation requirement changes from a ratio of 1/4 acre planted for every 1 acre removed to a ratio of 2 acres planted for every 1 acre removed.
Exhaustion of efforts to minimize cutting or clearing of trees
(c) After every reasonable effort to minimize the cutting or clearing of trees and other woody plants is exhausted in the development of a subdivision plan and grading and sediment control activities and implementation of the forest conservation plan, the forest conservation plan shall provide for reforestation, or payment into the Forest Conservation Fund, according to the formula set forth in subsection (b) of this section and consistent with the following forest conservation thresholds for the applicable land use category:
(1) Agricultural and resource areas: 50% of net tract area;
(2) Medium density residential areas: 25% of net tract area;
(3) Institutional development areas: 20% of net tract area;
(4) High density residential areas: 20% of net tract area;
(5) Mixed use and planned unit development areas: 15% of net tract area; and
(6) Commercial and industrial use areas: 15% of net tract area.
Net tract areas above forest conservation threshold
(d)(1) Subject to the provisions of paragraph (2) of this subsection, for all existing forest cover measured to the nearest 1/10 acre cleared on the net tract area above the applicable forest conservation threshold, the area of forest removed shall be reforested at a ratio of 1/4 acre planted for every 1 acre removed.
(2) Each acre of forest retained on the net tract area above the applicable forest conservation threshold shall be credited against the total number of acres required to be reforested under paragraph (1) of this subsection.
Net tract areas below forest conservation threshold
(e) For all existing forest cover measured to the nearest 1/10 acre cleared on the net tract area below the applicable forest conservation threshold, the area of forest removed shall be reforested at a ratio of 2 acres planted for every 1 acre removed.
Deadlines for reforestation requirements
(f)(1) The reforestation requirements under this section shall be accomplished within 1 year or 2 growing seasons after completion of the development project.
(2) If reforestation cannot be reasonably accomplished on-site or off-site, the requirement to contribute money to a Forest Conservation Fund under § 5-1610 of this subtitle shall be met within 90 days after completion of the development project.
Adoption of more stringent thresholds or requirements by local authority
(g) A unit of local government with planning and zoning authority may adopt forest conservation thresholds and afforestation and reforestation requirements as part of its local forest conservation program that are more stringent than the forest conservation thresholds and afforestation and reforestation requirements in this section.

Credits

Added by Acts 1991, c. 255, § 1, eff. July 1, 1991. Amended by Acts 1992, c. 22, § 1; Acts 1997, c. 559, § 2, eff. Oct. 1, 1997; Acts 2017, c. 794, § 1, eff. June 1, 2017; Acts 2017, c. 795, § 1, eff. June 1, 2017.
MD Code, Natural Resources, § 5-1606, MD NAT RES § 5-1606
Current through legislation effective through April 9, 2023, from the 2024 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.
End of Document