Application of section
(a) This section applies to a project by an investor-owned gas company, electric company, or combination gas and electric company involving the construction, reconstruction, installation, demolition, restoration, or alteration of any underground gas or electric infrastructure of the company, and any related traffic control activities.
In general
(b) An investor-owned gas company, electric company, or combination gas and electric company shall require a contractor or subcontractor on a project described in subsection (a) of this section to pay its employees not less than the prevailing wage rate determined by the Commissioner of Labor and Industry under Title 17, Subtitle 2 of the State Finance and Procurement Article.

Credits

Added by Acts 2021, 1st Sp. Sess., c. 12, § 1, eff. Jan. 5, 2022; Acts 2021, 1st Sp. Sess., c. 21, § 1, eff. Jan. 5, 2022.