§ 12-605. Cut-in certificate required before electrical current turned on

West's Annotated Code of MarylandPublic SafetyEffective: October 1, 2010

West's Annotated Code of Maryland
Public Safety (Refs & Annos)
Title 12. Building and Material Codes; Other Safety Provisions (Refs & Annos)
Subtitle 6. Electrical Code (Refs & Annos)
Effective: October 1, 2010
MD Code, Public Safety, § 12-605
§ 12-605. Cut-in certificate required before electrical current turned on
Cut-in certificate
(a) Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut-in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.
Qualified inspector
(b) Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.

Credits

Added by Acts 2010, c. 127, § 1, eff. Oct. 1, 2010.
MD Code, Public Safety, § 12-605, MD PUBLIC SAFETY § 12-605