§ 7-528. Effective date of qualified rate orders

West's Annotated Code of MarylandPublic UtilitiesEffective: December 14, 2022

West's Annotated Code of Maryland
Public Utilities (Refs & Annos)
Division I. Public Services and Utilities [Titles 1-15] (Refs & Annos)
Title 7. Gas, Electric, and Water Companies (Refs & Annos)
Subtitle 5. Electric Industry Restructuring (Refs & Annos)
Part III. Rate Stabilization (Refs & Annos)
Effective: December 14, 2022
MD Code, Public Utilities, § 7-528
Formerly cited as MD PUBLIC UTIL COMP § 7-528
§ 7-528. Effective date of qualified rate orders
Effective date
(a) A qualified rate order shall become effective in accordance with its terms.
Charges not subject to reduction, impairment, or adjustment
(b) After a qualified rate order becomes effective, the qualified rate order and the qualified rate stabilization charges authorized in the qualified rate order are irrevocable and are not subject to reduction, impairment, or adjustment by further action of the Commission except in accordance with §§ 7-531, 7-533, and 7-534 of this subtitle.
Qualified rate order not subject to rehearing
(c)(1) A qualified rate order is not subject to rehearing by the Commission.
(2) A qualified rate order may be reviewed by appeal only to the Circuit Court of Baltimore City by a party to the proceeding filed within 15 days after the qualified rate order is signed by the Commission.
(3) The judgment of the circuit court may be reviewed only by direct appeal to the Supreme Court of Maryland filed within 15 days after entry of judgment.
(4) All appeals shall be heard and determined by the circuit court and by the Supreme Court of Maryland as expeditiously as possible with lawful precedence over other matters.
(5) Review on appeal shall be based solely on the record before the Commission and briefs to the courts and shall be limited to whether the qualified rate order conforms to the Constitution and laws of this State and the United States and is within the authority of the Commission under this subtitle.
(6) The review process in this subsection shall be the exclusive remedy to challenge or review a qualified rate order.

Credits

Added by Acts 2006, 1st Sp. Sess., c. 5, § 1, eff. June 23, 2006. Amended by Acts 2023, c. 49, § 6.
MD Code, Public Utilities, § 7-528, MD PUBLIC UTIL § 7-528
Current through legislation effective through April 9, 2023, from the 2024 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.