§ 7-525. Recovery of actual costs of deferral
West's Annotated Code of MarylandPublic Utilities
MD Code, Public Utilities, § 7-525
Formerly cited as MD PUBLIC UTIL COMP § 7-525
§ 7-525. Recovery of actual costs of deferral
(a) The Commission may authorize an electric company to recover, as additional rate stabilization costs, the actual cost to the electric company of carrying the deferred expenses as regulatory assets under short-term and long-term deferral plans.
(b) The actual cost is equal to the deferred expenses as regulatory assets multiplied by the electric company's cost of debt.
Credits
Added by Acts 2006, 1st Sp. Sess., c. 5, § 1, eff. June 23, 2006.
MD Code, Public Utilities, § 7-525, MD PUBLIC UTIL § 7-525
Current through legislation effective through May 8, 2023, from the 2023 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.