§ 7-205. Modification of power plants
West's Annotated Code of MarylandPublic Utilities
MD Code, Public Utilities, § 7-205
Formerly cited as MD PUBLIC UTIL COMP § 7-205
§ 7-205. Modification of power plants
(a)(1) In this section, “modification” means a physical alteration of, replacement of, or other change to the facilities at a power plant, or a change in the fuel used by the plant, that could result in a change of the air emissions from the plant or from a generating unit of the plant.
(b) Subject to subsections (c) through (e) of this section, a person may not commence a modification without the prior approval of the Commission under this title.
(c)(1) Unless the Commission orders otherwise, an application for a modification to a power plant shall be filed with the Commission at least 180 days before the date on which the modification is to commence.
(d) The Commission shall render its decision within 150 days after the day the application is filed.
Credits
Added by Acts 1998, c. 8, § 2, eff. Oct. 1, 1998. Amended by Acts 2001, c. 347, § 1, eff. July 1, 2001; Acts 2006, c. 162, § 1, eff. July 1, 2006.
Formerly Art. 78, § 54-I.
MD Code, Public Utilities, § 7-205, MD PUBLIC UTIL § 7-205
Current with all legislation from the 2023 Regular Session of the General Assembly. Some statute sections may be more current, see credits for details.
End of Document |