§ 2671. Temporary Closure Requirements.
23 CA ADC § 2671Barclays Official California Code of Regulations
23 CCR § 2671
§ 2671. Temporary Closure Requirements.
(b) The monitoring required pursuant to the permit may be modified by the local agency during the temporary closure period. In making a decision to modify monitoring requirements, the local agency shall consider the need to maintain monitoring in order to detect unauthorized releases that may have occurred during the time the underground storage tank was used but that have not yet been detected. In all cases, corrosion protection shall continue to be operated.
(d) At the end of a temporary closure period over 12 months, including any extension granted by the local agency, the owner may reuse the underground storage tank only if the tank meets the requirements of Article 3 for new underground storage tanks or is upgraded to meet the requirements of Article 6.
(e) All new and existing underground storage tank systems which have been temporarily closed must continue to comply with repair and recordkeeping requirements, release reporting and investigation requirements, and release response and corrective action requirements specified in this chapter and Chapter 6.7 of the Health and Safety Code.
Credits
Note: Authority cited: Sections 25299.3 and 25299.7, Health and Safety Code. Reference: Section 25298, Health and Safety Code; 40 CFR 280.70 and 281.36(a)(1).
History
1. Amendment filed 8-9-91 as an emergency; operative 8-9-91. Text remains in effect uninterrupted pursuant to Health and Safety Code section 25299.7 (Register 92, No. 14).
2. Editorial correction of printing errors in History 1 (Register 92, No. 43).
3. Amendment of section and Note filed 4-5-94; operative 5-5-94 (Register 94, No. 14).
This database is current through 5/10/24 Register 2024, No. 19.
Cal. Admin. Code tit. 23, § 2671, 23 CA ADC § 2671
End of Document |