Home Table of Contents

§ 1314. Natural Gas System Analysis.

20 CA ADC § 1314Barclays Official California Code of Regulations

Barclays California Code of Regulations
Title 20. Public Utilities and Energy
Division 2. State Energy Resources Conservation and Development Commission (Refs & Annos)
Chapter 3. Data Collection
Article 1. Quarterly Fuel and Energy Reports
20 CCR § 1314
§ 1314. Natural Gas System Analysis.
(a) Each gas utility with annual natural gas deliveries of 200 million therms or more in both of the two calendar years preceding the required data filing shall, on August 1, 2019 and on March 15 every year thereafter, via secure electronic method, provide files that are used by the gas utility to conduct gas hydraulic modeling for its natural gas system during the previous calendar year, including the scenarios (1) - (4) below:
(1) average summer day (June through September);
(2) average winter day (November through March);
(3) 1-in-10 peak summer and winter day; and
(4) any additional summer and winter day representing demand higher than that identified in subdivisions (1)-(3) above.
(b) The files provided need not identify natural gas infrastructure dedicated to retail customers other than power plants.
(c) Current identification information and current project characteristics for underground gas storage projects. Owners of underground gas storage projects are required to submit the following project identification information and project characteristic information to the California Energy Commission on a quarterly basis. Owners of underground gas storage projects are to express working gas capacity and total storage capacity in thousand cubic feet (Mcf) and maximum deliverability in Mcf/day.
(1) Storage Field Name
(2) Reservoir Name
(3) Location County
(4) Type of Facility - Aquifer, Depleted Field, or Salt Formation
(5) Field Status - either Active or Inactive
(6) Company Name
(7) Contact First and Last Name
(8) Phone Number
(9) Company Address
(10) Company Email Address
(11) Working Gas Capacity (Mcf)
(12) Total Storage Field Capacity (Mcf)
(13) Maximum Deliverability (Mcf/day)
(d) Daily underground gas storage project information. Owners of underground gas storage projects are required to submit information on base gas, working gas, total gas in storage, withdrawal, and injection for each calendar day. Volumes shall be expressed in Mcf. If the volumes submitted require true-up, provide notation for any true-ups required. Owners of underground gas storage projects are required to submit the following information for each calendar day on a quarterly basis:
(1) Report Day (Month, Day, and Year)
(2) Base Gas (Mcf)
(3) Working Gas (Mcf)
(4) Total Gas in Storage, which is the sum of base and working gas
(5) Injections (Mcf)
(6) Withdrawals (Mcf)

Credits

Note: Authority cited: Sections 25213, 25218(e) and 25320, Public Resources Code. Reference: Sections 25005.5, 25216, 25216.5, 25300-25303, 25303.5, 25305, 25400, 25401, 25401.2, 25403 and 25602, Public Resources Code.
History
1. New section filed 5-29-2018; operative 7-1-2019 (Register 2018, No. 22).
2. New subsections (c)-(d)(6) filed 12-30-2021; operative 1-1-2022 pursuant to Government Code section 11343.4(b)(3) (Register 2021, No. 53).
This database is current through 5/24/24 Register 2024, No. 21.
Cal. Admin. Code tit. 20, § 1314, 20 CA ADC § 1314
End of Document