§ 841. Time for Completion.

23 CA ADC § 841BARCLAYS OFFICIAL CALIFORNIA CODE OF REGULATIONS

Barclays Official California Code of Regulations Currentness
Title 23. Waters
Division 3. State Water Resources Control Board and Regional Water Quality Control Boards
Chapter 2. Appropriation of Water
Article 20. Diligence Required -Extensions of Time
23 CCR § 841
§ 841. Time for Completion.
In determining the period of time to be allowed to build diversion works and apply the water to full beneficial use, the particular conditions surrounding each case will govern. In every case the matter must be pressed with due diligence considering the size of the project and the obstacles to be overcome.
Note: Authority cited: Section 1058, Water Code. Reference: Sections 1250, 1252 and 1260, Water Code.
HISTORY
1. Renumbering and amendment of Section 777 to Section 841 filed 1-16-87; effective thirtieth day thereafter (Register 87, No. 10). For prior history, see Register 60, No. 5.
This database is current through 6/24/22 Register 2022, No. 25
23 CCR § 841, 23 CA ADC § 841