§ 3955. Basin Plan Amendment Incorporating a Total Maximum Daily Load (TMDL) and TMDL Implement...

23 CA ADC § 3955BARCLAYS OFFICIAL CALIFORNIA CODE OF REGULATIONS

Barclays Official California Code of Regulations Currentness
Title 23. Waters
Division 4. Regional Water Quality Control Boards
Chapter 1. Water Quality Control Plans, Policies, and Guidelines
Article 6. Lahontan Region
23 CCR § 3955
§ 3955. Basin Plan Amendment Incorporating a Total Maximum Daily Load (TMDL) and TMDL Implementation Program to Control Phosphorus Loading to Indian Creek Reservoir.
The goal of this TMDL is a change from eutrophic to mesotrophic conditions, which should provide adequate support for aquatic life and recreational beneficial uses. Attainment of the numeric target for total phosphorus (0.02 mg/L as an annual mean concentration in the water column) is projected to occur within approximately 21 years after final approval of the TMDL (2024). Attainment of other numeric targets and narrative water quality objectives related to protection of beneficial uses is also projected to occur by that date.
The TMDL assigns a loading capacity for phosphorus loading to Indian Creek Reservoir, as a net annual load of 82 pounds of total phosphorus in the water column. Attainment of the loading capacity and numeric target will require an 87 percent reduction in internal phosphorus loading from the sediment and a 75 percent reduction in external loading to the reservoir from the surrounding watershed and the tributary inflow.
The TMDL implementation program will use an adaptive management approach. It establishes a process and schedule for selection and implementation of specific control measures. Such measures will include best management practices to control external sources, and in-lake control methods to control phosphorus loading from the sediment. Examples of potential in-lake controls include measures to remove phosphorus-laden sediment, reduce phosphorus release from sediment, and/or increase flushing of phosphorus from the reservoir. Implementation will be the responsibility of the South Tahoe Public Utility District (STPUD), which manages the reservoir and its tributary flow; the U.S. Bureau of Land Management, which owns the watershed contributing surface runoff to the reservoir; and public and private landowners in the watershed of the tributary inflow.
The Lahontan Regional Board will use its existing authority, including the three-tier compliance approach (ranging from self-determined implementation to regulatory action) in the statewide Nonpoint Source Management Plan and Rangeland Water Quality Management Plan, to ensure implementation of the TMDL.
The TMDL implementation program includes continued monitoring of water quality in the reservoir and its tributary inflow, and periodic inspection of BMPs once they have been installed. The adaptive management approach includes flexibility for changes in the existing monitoring program over time.
If progress toward implementation and attainment of TMDL targets and indicators is not satisfactory at the conclusion of the second comprehensive review (in 2013), or if monitoring shows support of beneficial uses at phosphorus concentrations higher than mandated by the target, Regional Board staff will evaluate the need for revision of the TMDL and/or the implementation program.
Specifics of the TMDL implementation program are as follows
Summary of TMDL Implementation Program
Implementation Process
Schedule
 
Stakeholder group is convened by Regional
By 4 months after final
Board staff
approval of TMDL
 
Regional Board staff and stakeholders
By 1 year after final approval
identify specific sites needing BMPs to
of TMDL
control external sources of phosphorus loading
 
STPUD submits plan for Regional Board
By 15 months after final
approval on proposed action(s) to control
approval of TMDL
internal phosphorus loading
 
Progress toward BMP implementation
By 3 years after final approval
reviewed; need for Regional Board regulatory
of TMDL
action considered
 
Controls for internal and external sources
By 2013
phosphorus loading are fully implemented
 
Review of monitoring data in relation to
Ongoing
indicators and targets
 
Comprehensive review of monitoring data and
At five-year intervals
progress toward implementation and
following final approval of
attainment of targets
TMDL
 
Consideration of needs for revisions in TMDL
After 2013
 
HISTORY
1. New section summarizing regulatory changes filed 4-14-2003; Basin Plan revisions adopted by the Lahontan Regional Board 7-24-2002 and approved by the State Water Resources Control Board 1-22-2003. Approved by OAL pursuant to Government Code section 11353 and effective on 4-14-2003 (Register 2003, No. 16).