§ 612.61. Utility Crossing State Water Project Open Aqueduct.
23 CA ADC § 612.61Barclays Official California Code of Regulations
23 CCR § 612.61
§ 612.61. Utility Crossing State Water Project Open Aqueduct.
(c) Clearance between encroaching utilities and the top of the existing or future aqueduct lining shall be a minimum of twelve (12) inches. If this minimum clearance is reduced by subsidence or by future departmental modifications to the canal lining, the required minimum clearance shall be re-established at the permittee's cost and expense.
(e) Directional drilling under an open canal may be considered if a minimum clearance of twenty-five (25) feet is maintained between the casing, or carrier pipe if no casing will be installed, and the bottom of the canal lining. A geotechnical report shall be submitted for review by the Department prior to approval of the proposed utility crossing. Deviations from Section 612.63 (c), Article 6 of these Regulations (regarding casing requirements) may be considered by the Department if the alternate casing will not increase the potential for damage to, or contamination of, State Water Project facilities or right-of-way.
Credits
Note: Authority cited: Section 12899.9, Water Code. Reference: Sections 12899, 12899.1(a), 12899.1(c) and 12899.2, Water Code.
History
1. New section filed 4-22-2015; operative 7-1-2015 (Register 2015, No. 17).
This database is current through 6/21/24 Register 2024, No. 25.
Cal. Admin. Code tit. 23, § 612.61, 23 CA ADC § 612.61