§ 20330. SWRCB--Liners. (C15: § 2542)

27 CA ADC § 20330Barclays Official California Code of Regulations

Barclays California Code of Regulations
Title 27. Environmental Protection
Division 2. Solid Waste (Refs & Annos)
Subdivision 1. Consolidated Regulations for Treatment, Storage, Processing or Disposal of Solid Waste
Chapter 3. Criteria for All Waste Management Units, Facilities, and Disposal Sites
Subchapter 2. Siting and Design
Article 4. SWRCB--Waste Management Unit Construction Standards
27 CCR § 20330
§ 20330. SWRCB--Liners. (C15: § 2542)
(a) Performance Standard--Liners shall be designed and constructed to contain the fluid, including landfill gas, waste, and leachate, as required by Article 3 of this subchapter (§ 20240 et seq., and § 20310).
(b) Clay Liners--Clay liners for a Class II Unit shall be a minimum of 2 feet thick and shall be installed at a relative compaction of at least 90 percent. For a Class III landfill, a clay liner, if required, shall be a minimum of 1-foot thick and shall be installed at a relative compaction of at least 90 percent. For MSW landfills subject to the liner requirements in the federal MSW regulations of 40CFR258, after the Federal Deadline for liners at that Unit, the requirements of this paragraph are superseded by those of SWRCB Resolution No. 93-62 for all portions of the Unit outside the Existing Footprint.
(c) FMLs--Flexible membrane liners (“FMLs”, or synthetic liners) shall have a minimum thickness of 40 mils (i.e., 0.040″). For an MSW landfill subject to the liner requirements in the federal MSW regulations (40CFR258), after the Federal Deadline for liners at that Unit, the requirements of this paragraph are superseded by those of SWRCB Resolution No. 93-62 for all portions of the Unit outside the Existing Footprint.
(d) Lined Area--Liners shall be installed to cover all natural geologic materials (at the Unit) that are likely to be in contact with waste (including landfill gas or leachate).
(e) S.I. With Replaceable Liner--A Class II surface impoundment may have a single clay liner with a hydraulic conductivity of 1x10-6 cm/sec (i.e., 1 foot/year) or less if the liner is removed or replaced before the last 25 percent (minimum 1 foot thickness) of the liner is penetrated by fluid, including waste or leachate. The method used to determine seepage velocity shall be included with the calculations of liner penetration.

Credits

Note: Authority cited: Section 1058, Water Code. Reference: Sections 13172 and 13360, Water Code; and Section 43103, Public Resources Code.
History
1. New section filed 6-18-97; operative 7-18-97 (Register 97, No. 25).
This database is current through 4/26/24 Register 2024, No. 17.
Cal. Admin. Code tit. 27, § 20330, 27 CA ADC § 20330