§ 15177. Subsequent Projects Within the Scope of the MEIR.
14 CA ADC § 15177Barclays Official California Code of Regulations
14 CCR § 15177
§ 15177. Subsequent Projects Within the Scope of the MEIR.
(2) The lead agency for the subsequent project prepares an initial study on the proposal. The initial study shall analyze whether the subsequent project was described in the Master EIR and whether the subsequent project may cause any additional significant effect on the environment which was not previously examined in the Master EIR.
(3) The lead agency for the subsequent project determines, on the basis of written findings, that no additional significant environmental effect will result from the proposal, no new additional mitigation measures or alternatives may be required, and that the project is within the scope of the Master EIR. “Additional significant environmental effect” means any project-specific effect which was not addressed as a significant effect in the Master EIR.
(c) Whether a subsequent project is within the scope of the Master EIR is a question of fact to be determined by the lead agency based upon a review of the initial study to determine whether there are additional significant effects or new additional mitigation measures or alternatives required for the subsequent project that are not already discussed in the Master EIR.
Credits
Note: Authority cited: Section 21083, Public Resources Code. Reference: Sections 21157, 21157.6 and 21158, Public Resources Code.
History
1. New section filed 5-27-97; operative 5-27-97 pursuant to Government Code section 11343.4(d) (Register 97, No. 22).
2. Change without regulatory effect amending subsection (b) and Note filed 10-6-2005 pursuant to section 100, title 1, California Code of Regulations (Register 2005, No. 40).
This database is current through 4/26/24 Register 2024, No. 17.
Cal. Admin. Code tit. 14, § 15177, 14 CA ADC § 15177
End of Document |