Home Table of Contents

§ 609. Contracting in Phases.

11 CA ADC § 609Barclays Official California Code of RegulationsEffective: October 1, 2022

Barclays California Code of Regulations
Title 11. Law
Division 1. Attorney General
Chapter 6. Selection Process for Private Architectural and Engineering Firms
Effective: October 1, 2022
11 CCR § 609
§ 609. Contracting in Phases.
(a) If the Chief determines it is necessary or desirable to have a project performed in phases, it will not be necessary to negotiate the total contract amount or compensation provisions in the initial instance, provided that:
(1) The Chief has determined that the selected firm is best qualified to perform the entire project at a fair and reasonable cost; and
(2) The contract states that the Department may, at its option, use that firm to perform other phases of the project and that the firm will accept a fair and reasonable price for subsequent phases to be later negotiated and reflected in a subsequent written instrument.
(b) The procedures established in this chapter with regard to estimates and negotiation shall otherwise be applicable.

Credits

Note: Authority cited: Section 4526, Government Code. Reference: Sections 4526 and 4528, Government Code.
History
1. New section filed 7-22-2022; operative 10-1-2022 (Register 2022, No. 29).
This database is current through 5/24/24 Register 2024, No. 21.
Cal. Admin. Code tit. 11, § 609, 11 CA ADC § 609
End of Document