Home Table of Contents

§ 1020.7. Permit Fees for Park Construction or Alteration.

25 CA ADC § 1020.7BARCLAYS OFFICIAL CALIFORNIA CODE OF REGULATIONS

Barclays Official California Code of Regulations Currentness
Title 25. Housing and Community Development
Division 1. Housing and Community Development
Chapter 2. Mobilehome Parks and Installations
Article 1. Administration and Enforcement
25 CCR § 1020.7
§ 1020.7. Permit Fees for Park Construction or Alteration.
(a) Any person submitting an application for a permit to construct with plans not having a department standard plan approval, shall pay the following fees, as applicable:
(1) Permit Fee. For the purpose of determining fees, the enforcement agency may establish the permit fee in accordance with subsection (f) or (g) of this section as appropriate. However, the minimum permit fee shall be one hundred ninety-six dollars ($196) provided the initial related inspection associated with this permit does not exceed one hour. When the related inspection exceeds one hour, the following fees shall apply:
(A) Second and subsequent whole hours: eighty-two dollars ($82).
(B) Each thirty (30) minutes, or fractional part thereof: forty-one dollars ($41).
(2) Plan Check Fee. One-half (1/2) of the combined total of construction, mechanical, plumbing, and electrical permit fees. However, the minimum fee shall be ten dollars ($10).
(b) Reinspection Fee. One hundred seventy-eight dollars ($178) provided the related inspection does not exceed one hour. When the related inspection exceeds one hour, the following fees shall apply:
(1) Second and subsequent whole hours: eighty-two dollars ($82).
(2) Each thirty (30) minutes, or fractional part thereof: forty-one dollars ($41).
(c) When any person files applications simultaneously to construct two (2) or more permanent buildings, or accessory buildings or structures which are identical and are within the same park, only one (1) plan check fee shall be required.
(d) Electrical, mechanical, and plumbing permit fees shall not exceed those contained in this chapter.
(e) When plans and specifications fail to comply with the requirements of this chapter, the enforcement agency shall notify the applicant in writing, stating in what respects the plans do not comply. The applicant shall correct the plans and/or specifications and resubmit them to the enforcement agency. The following fees are required for each resubmission of plans or specifications subsequent to the initial plan check:
(1) Plan Check Fee: Two hundred three dollars ($203) provided the related plan check does not exceed one hour. When the related plan check exceeds one hour, the following shall apply:
(A) Second and subsequent whole hours: ninety-two dollars ($92).
(B) Each thirty (30) minutes, or fractional part thereof: forty-six dollars ($46).
(f) Fees for construction or alteration of facilities and installations on lots and within parks shall be the sum of the following categories comprising the proposed work subject to the minimum amounts specified in subsection (a)(1):
(1) For each lot $5.75
(2) Electrical Permit Fees.
Each park electrical service 14.00
Each unit substation or secondary distribution transformer 10.50
Each alteration or replacement of a service or
a transformer 10.50
Each park lot electrical service equipment 7.00
Each alteration, repair, or replacement of a park lot electrical service equipment 7.00
Each street light including circuit conductors and control equipment 3.00
(3) Plumbing Permit Fees.
Each park sewage drainage system 14.00
Each private sewage disposal system or park water treatment installation 14.00
Each lot drain inlet 7.00
Each alteration or repair of drainage or vent piping 7.00
Each park water distribution system 7.00
Each park lot water service outlet or outlets at the same location 4.25
Each fire hydrant or riser 4.25
Each individual lot water conditioning installation 4.25
Each alteration, repair or replacement of water fixtures or equipment 4.25
(4) Gas Piping Permit Fees.
Each park gas piping system 7.00
Each installation of a liquefied petroleum or natural gas tank of 60 gallon capacity or more 7.00
Each gas riser outlet 4.25
Each alteration, repair, or replacement of park's gas piping system 4.25
(5) Each installation of equipment regulated by this chapter for which no other fee is listed 7.00
(g) Permit fees for a permit to construct accessory buildings or structures without a standard plan approval from the department, and foundation systems, permanent buildings, and/or electrical, mechanical, and plumbing installations within or on permanent buildings, or accessory buildings or structures shall be the sum of the following categories comprising the proposed work subject to the minimum amounts specified in subsection (a)(1).
(1) Table A. Construction Permit Fees.
Total Valuation
Fee
$2,000 or less
 
$45.00
$2,001 to $25,000
 
$45.00 for the first $2,000 plus
$9.00 for each additional thousand or
fraction thereof, to and including $25,000.
$25,001 to $50,000
 
$252.00 for the first $25,000
plus $6.50 for each additional thousand
or fraction thereof, to and including
$50,000.
$50,001 to $100,000
 
$414.50 for the first $50,000
plus $4.50 for each additional thousand or
fraction thereof, to and including $100,000.
$100,001 to $500,000
 
$639.50 for the first $100,000
plus $3.50 for each additional thousand or
fraction thereof, to and including $500,000.
$500,001 to $1,000,000
 
$2,039.50 for the first $500,000
plus $3.00 for each additional thousand or
fraction thereof, to and including
$1,000,000.
$1,000,001 and up
 
$3,539.50 for the first $1,000,000
plus $2.00 for each additional thousand or
fraction thereof.
(2) Table B. Mechanical and Plumbing Permit Fees.
Each plumbing fixture, trap, set of fixtures on one trap, including
water, drainage piping and backflow protection therefore
 
$3.00
Each building sewer
 
14.00
Each private sewage disposal system
 
14.00
Each water heater and/or vent
 
7.00
Each gas piping system for one to five outlets
 
7.00
Each gas piping system for six or more outlets, per outlet
 
1.50
Each gas regulator
 
1.50
Each water branch service outlet or outlets at the same location, or
each fixture supply
 
1.00
Each installation of water treating equipment
 
7.00
Alteration or repair of water piping or water treating equipment
 
7.00%
Alteration or repair of drainage or vent piping
 
7.00
Each lawn sprinkler system on any one meter, including backflow
protection devices
 
7.00
Vacuum breakers or backflow protective devices on tanks, vats, etc.,
or for installation on unprotected plumbing fixtures: one to five
 
3.00
over five, each additional
 
1.00
The installation or relocation of each forced-air or gravity-type
furnace or burner, including ducts and vents attached to such
appliance, up to and including 100,000 Btu
 
14.00
The installation or relocation of each forced-air or gravity-type
furnace or burner, including ducts and vents attached to such
appliance over 100,000 Btu
 
21.00
The installation or relocation of each floor furnace, including vent
 
7.00
The installation or relocation of each suspended heater, recessed
wall heater or floor-mounted unit heater
 
7.00
The installation, relocation or replacement of each appliance vent
installed and not included in an appliance permit
 
7.00
The repair of, alteration of, or addition to each heating appliance,
refrigeration unit, comfort cooling unit, absorption unit, or each
comfort heating, cooling, absorption, or evaporative cooling
system, including installation of controls
 
14 .00
The installation or relocation of each boiler or compressor to and
including three horsepower or each absorption system to and
including 100,000 Btu
 
14.00
The installation or relocation of each boiler or compressor over three
horsepower or each absorption system over 100,000 Btu.
 
21.00
Each air handling unit, including ducts attached thereto
 
7.00
NOTE:This fee shall not apply to an air handling unit which is a portion of a factory-assembled appliance, comfort cooling unit, evaporative cooler or absorption unit for which a permit is required elsewhere in this chapter.
For each evaporative cooler other than portable type
 
7.00
For each vent fan connected to a single duct
 
3.00
For each vent ventilation system which is not a portion of any
heating or air conditioning system authorized by a permit
 
7.00
Each installation of equipment regulated by this chapter for
which no other fee is listed
 
7.00
(3) Table C. Electrical Permit Fees.
Each wiring outlet where current is used or controlled, except
services, sub-feeders and meter outlets
 
.35
Each fixture, socket or other lamp holding device
 
.35
Each motor of not more than 50 h.p
 
4.25
Each motor of more than 50 h.p
 
10.50
Each mercury arc lamp and equipment
 
1.00
Each range, water heater or clothes dryer installation
 
7.00
Each space heater or infrared heat installation
 
1.50
Each stationary cooking unit, oven, or space heater
 
1.50
Each garbage disposer, dishwasher, or fixed motor-operated
appliance not exceeding 1/2 h.p
 
1.50
Working light in buildings in course of construction or undergoing
repairs, or where temporary lighting is to be used
 
3.00
Each incandescent electric sign
 
1.50
Electric signs or outline lighting, luminous gas type with: 1 to 4
transformers
 
3.00
Additional transformers, each
 
.35
Each rectifier and synchronous converter, per K.W
 
.35
Each additional circuit for a mobile home accessory building
or structure or other electrical equipment
 
1.50
Each service:
600 volts or less, not over 200-amperes
 
7.00
600 volts or less, over 200-amperes
 
10.00
Over 600 volts
 
14.00
Each installation of equipment regulated by this chapter for
which no other fee is listed
 
7.00
Note: Authority cited: Sections 18300, 18502.5 and 18552, Health and Safety Code. Reference: Sections 18502, 18502.5 and 18503, Health and Safety Code.
HISTORY
1. Renumbering of former section 1022 to new section 1020.7, including amendment of section heading and section, filed 7-6-2004; operative 7-6-2004 pursuant to Government Code section 11343.4 (Register 2004, No. 28).
2. Amendment filed 12-29-2005; operative 1-1-2006 pursuant to Government Code section 11343.4 (Register 2005, No. 52).
This database is current through 3/13/20 Register 2020, No. 11
25 CCR § 1020.7, 25 CA ADC § 1020.7
End of Document© 2020 Thomson Reuters. No claim to original U.S. Government Works.