§ 1009. Permit to Operate -Penalty Fees.

25 CA ADC § 1009BARCLAYS OFFICIAL CALIFORNIA CODE OF REGULATIONS

Barclays Official California Code of Regulations Currentness
Title 25. Housing and Community Development
Division 1. Housing and Community Development
Chapter 2. Mobilehome Parks and Installations
Article 1. Administration and Enforcement
25 CCR § 1009
§ 1009. Permit to Operate -Penalty Fees.
(a) Permits to operate shall have the following penalty fees applied as applicable:
(1) When an application is submitted thirty (30) days after the due date, the permit to operate fees shall be increased an amount equal to ten (10) percent of the established fee.
(2) When an application is submitted sixty (60) or more days late, the permit to operate fees shall be increased an amount equal to one hundred (100) percent of the established fee.
(3) Any park commencing operation without a valid permit to operate shall pay double the established fees and those fees shall be due upon demand of the enforcement agency.
(b) The postmark shall be used to determine the submittal date for imposing annual permit to operate penalty fees prescribed by Health and Safety Code section 18506.
Note: Authority cited: Section 18300, Health and Safety Code. Reference: Sections 18504 and 18506, Health and Safety Code.
HISTORY
1. Renumbering and amendment of former Section 1016 to Section 1009 filed 8-22-85; effective upon filing pursuant to Government Code Section 11346.2(d) (Register 85, No. 36).
2. Amendment filed 11-29-88; operative 12-29-88 (Register 88, No. 52).
3. Amendment of section and Notefiled 7-6-2004; operative 7-6-2004 pursuant to Government Code section 11343.4 (Register 2004, No. 28).