Home Table of Contents

§ 3502. The Reclamation Plan.

14 CA ADC § 3502Barclays Official California Code of Regulations

Barclays California Code of Regulations
Title 14. Natural Resources
Division 2. Department of Conservation
Chapter 8. Mining and Geology
Subchapter 1. State Mining and Geology Board
Article 1. Surface Mining and Reclamation Practice
14 CCR § 3502
§ 3502. The Reclamation Plan.
(a) Objectives. Reclamation plans shall be developed to attain the objectives of Public Resources Code Section 2712(a)-(c).
(b) Reclamation Plan Elements. In addition to the information required by Public Resources Code Section 2772, the following elements shall be included in the reclamation plan:
(1) The environmental setting of the site of operations and the effect that possible alternate reclaimed site conditions may have upon the existing and future uses of surrounding lands.
(2) The public health and safety, giving consideration to the degree and type of present and probable future exposure of the public to the site.
(3) The designed steepness and proposed treatment of the mined lands' final slopes shall take into consideration the physical properties of the slope material, its probable maximum water content, landscaping requirements, and other factors. In all cases, reclamation plans shall specify slope angles flatter than the critical gradient for the type of material involved. Whenever final slopes approach the critical gradient for the type of material involved, regulatory agencies shall require an engineering analysis of the slope stability. Special emphasis on slope stability and design shall be necessary when public safety or adjacent property may be affected.
(4) Areas mined to produce additional materials for backfilling and grading, as well as settlement of filled areas, shall be considered in the reclamation plan. Where ultimate site uses include roads, building sites, or other improvements sensitive to settlement, the reclamation plans shall include compaction of the fill materials in conformance with good engineering practice.
(5) Disposition of old equipment.
(6) Temporary stream or watershed diversions.
(c) Adequacy. In judging the adequacy of a particular reclamation plan in meeting the requirements described herein and within the Act, the lead agency shall consider the physical and land-use characteristics of the mined lands and their surrounding area pursuant to Public Resources Code Section 2773.
(d) Each surface mining operation as defined in Public Resources Code Section 2735 and Title 14 California Code of Regulations Section 3501, shall have no more than one approved reclamation plan applicable to that operation except as described in subsection (i) to this section. An amended reclamation plan shall be approved by the lead agency prior to the commencement of activities determined to be a substantial deviation from the approved plan. For purposes of the Surface Mining and Reclamation Act of 1975 and regulations adopted pursuant thereto, a substantial deviation shall be defined as a change or expansion to a surface mining operation that substantially affects the completion of the previously approved reclamation plan, or that changes the end use of the approved plan to the extent that the scope of the reclamation required for the surface mining operation is substantially changed. In determining whether a change or expansion constitutes a substantial deviation, the lead agency shall take into consideration the following factors:
(1) A substantial increase in the disturbance of a surface area or in the maximum depth of mining;
(2) A substantial extension of the termination date of the mining operation as set out in the approved reclamation plan;
(3) Changes that would substantially affect the approved end use of the site as established in the reclamation plan;
(4) The consistency of any proposed change to the operation with the previously adopted environmental determinations.
(5) Any other changes that the lead agency deems substantial deviations as defined in this subsection.
(e) An amended reclamation plan shall be filed if the lead agency determines, after an inspection, that the surface mining operation can no longer be reclaimed in accordance with its approved reclamation plan. Such amended plan shall incorporate current reclamation standards as described in Chapter 9 (commencing with Section 2710) and Title 14 of the California Code of Regulations commencing with Section 3700.
(f) In the event that a proposed change is determined not to be a substantial deviation from an approved reclamation plan, then current reclamation standards need only apply to the amended portion of the plan. An amendment to the originally approved reclamation plan that includes an expanded operating area shall be approved by the lead agency prior to implementation of the activities in the expansion area.
(g) Should an expansion of an operation into an area not covered by an approved reclamation plan be determined by the lead agency to be a substantial deviation, an amended reclamation plan shall be prepared that ensures adequate reclamation for the surface mining operation. The amended reclamation plan shall incorporate current reclamation standards for the entire area governed by the plan that is impacted by the deviation. If reclamation has been substantially initiated at the time that a lead agency determines that an amended reclamation plan is required, the operator may complete reclamation of those areas according to the previously approved reclamation plan, except for those areas that are or will be affected by the proposed expanded mining activities which shall be subject to the requirements of the amended reclamation plan.
(h) Where a surface mining operation has in effect an approved reclamation plan and approved financial assurance covering a surface mining operation, and the mining operator proposes to utilize a new surface area, not included within the approved reclamation plan, for purposes of creating a new and separate pit, quarry, or other excavation, the operator may, at the option of the operator do one of two things:
(1) Amend the existing reclamation plan to encompass the new area designated for use as a pit, quarry, or excavation, together with any other changes necessary to make the reclamation plan, as amended, conform to the Act and these regulations. If such an amended plan is proposed, the amended plan must conform to the current reclamation standards required by the Act and the regulations, as to the new area(s) designated as a quarry, pit or excavation, and any processing facilities, roads, sumps, drainage systems or storage or processing areas, which that new area will utilize within the previously approved reclamation plan area or within the new area. Concurrently with the approval of the amended reclamation plan to encompass the new area operations, unless such a provision already is in the existing reclamation plan, the lead agency may require an amendment to the existing reclamation plan to provide for the immediate commencement of the reclamation of any mined lands which no longer are required for mining operations.
(2) Obtain approval of a new reclamation plan covering the new area and any facilities, roads, sumps, drainage systems, or storage or processing areas, utilized in connection with operations in the new area. Any areas encompassed within such plan shall conform to the reclamation standards of the Act and these regulations that are in effect at the time the reclamation plan is approved.
(i) The following exemptions to this section shall apply:
(1) Where a single surface mining operation has separate facilities located within different lead agency jurisdictions, and where these facilities are separated by a distinct and significant physical boundary such as a major highway, stream channel, or the like, the operator may obtain separate reclamation plans and financial assurances for the facilities from the lead agencies in which those facilities are located.
(2) Those surface mining operations that have more than one reclamation plan approved on or before October 1, 2002 shall not be subject to the requirements for a single reclamation plan as described in subsection (d) of this section unless new mining operations or substantial deviations to the operation are proposed after that date that require one of the plans to be amended.

Credits

Note: Authority cited: Section 2755, Public Resources Code. Reference: Sections 2712(a)-(c), 2756-2757, 2770 and 2772-2773, Public Resources Code.
History
1. Renumbering and amendment of former Section 3502 to Section 3501, and new Section 3502 filed 4-29-85; effective thirtieth day thereafter (Register 85, No. 18). For prior history, see Registers 82, No. 33 and 79, No. 35.
2. New subsections (d)-(i)(2) filed 10-3-2002; operative 11-2-2002 (Register 2002, No. 40).
This database is current through 3/15/24 Register 2024, No. 11.
Cal. Admin. Code tit. 14, § 3502, 14 CA ADC § 3502
End of Document