§ 1777.2. Production Facility Reporting Requirements.
14 CA ADC § 1777.2Barclays Official California Code of Regulations
14 CCR § 1777.2
§ 1777.2. Production Facility Reporting Requirements.
(b) Operators shall notify the local district office within 60 days after completing new construction, alteration, or decommissioning of a production facility, or reactivating an Out-of-Service tank . This notification report shall describe the activities and reference the production facilities that have been added, altered or decommissioned.
Credits
Note: Authority cited: Sections 3013 and 3270, Public Resources Code. Reference: Sections 3106, 3202 and 3270, Public Resources Code.
History
1. New section filed 12-30-2010; operative 1-29-2011 (Register 2010, No. 53).
This database is current through 5/10/24 Register 2024, No. 19.
Cal. Admin. Code tit. 14, § 1777.2, 14 CA ADC § 1777.2
End of Document |